Council to hold public hearing on Maxwell Street apartment complex
If approved, the complex would be the third high-density apartment complex approved on East Maxwell street in the last year and a half.
If approved, the project on the formal landfill with Edelen Renewables would create enough electricity to power about 5,300 homes.
On November 18th at 1pm, the Environmental Quality and Public Works Committee will discuss a potential solar energy project at the city's Haley Pike Landfill, a 687 acre site that spans Fayette and Clark counties. While the landfill itself is capped and closed, the city still deposits yard and construction waste at the Haley Pike site.
The city is currently finalizing negotiations with Edelen Renewables/Social Impact Solar to build solar panels across different sections of the site, including parts of the capped landfill. Under the current proposal, the city would lease the land to Edelen Renewables/Social Impact Solar but would not be involved in operations or contribute any funding to the project. The company estimates the 67.4 megawatt facility could produce enough electricity to power about 5,300 Kentucky homes.
While still in negotiations with LFUCG, Edelen Renewables is requesting a Letter of Intent to begin communications with the necessary regulatory agencies and utility companies. If the lease is finalized and approved, construction could begin as soon as late spring 2026.

Under the submitted proposal, Edelen Renewables would lease land from LFUCG at the Haley Pike site and install approximately 357 acres of solar panels and infrastructure. Some panels would be on top of existing capped landfills, which would require special mounting equipment to ensure that the caps are not damaged. Energy produced would be sent to Kentucky Utilities.
The lease would provide new revenue for LFUCG through lease payments, payments in lieu of taxes, and water quality management fees, but the exact dollar amounts are still being negotiated between the city and Edelen Renewables.
Edelen Renewables estimates the project would reduce greenhouse gas emissions by 37,193 metric tons of carbon equivalent per year, which is roughly equivalent to taking about 8,000 cars off the road.
If constructed on schedule, the solar facility would begin operating in December 2027 and continue until the lease ends in January 2049. After the end of the lease, Edelen Renewables would be responsible for removing all equipment and recycling the solar panels, a process known as decommissioning.
Edelen Renewables has also proposed a Community Benefit Plan that would include workforce training programs, educational partnerships with Fayette County Public Schools, and collaboration with city sustainability staff.
Installing solar power on the Haley Pike landfill site has been a topic for many years since the site's landfills were capped in 2011.
The timeline for this Letter of Intent and project is being impacted by recent changes to federal policy.
According to Edelen Renewables' presentation, losing this tax credit would mean the project loses a payment equal to about 35-40% of the project's value. The company says this would likely make the project "non-viable for financing."
The tax credit is so critical for this specific project because building on a closed landfill is significantly more expensive and riskier than building on open farmland. Without the federal tax credit, the company says a third-party developer would be unlikely to find the project financially feasible.
If the committee approves the Letter of Intent and Edelen Renewables would finalize lease negotiations in November and December 2025, the full negotiated lease would then come back to Council for approval in December 2025 or January 2026. Construction would begin in late spring or early summer 2026, with the facility becoming operational in December 2027. The project would operate through January 2049.